Arun AION site status

We are well aware of the curiosity and being safe in such conditions. so please find the site status of Arun Aion. Work as on 4 June 2021 1)External Plaster of double height terrace of Flat to 406 final coat plaster is in progress 2)Blockwork of touch up at flat no.306 to 406 is in progress 3)M sand shifting at 6&7 the floor is in progress 4)lift1 pardi & staircase1 casting work at 10 the floor is in progress 5)bottom fixing of 12th slab is in progress 6) Concealed stop cock fitting work at 2nd floor is going on. 7)Window grill making work is going on. 8) Ghadai work at 3rd floor & material shifting work is in progress .