Pune-Nashik semi high speed corridor

MahaRailLogo

PUNE: Deputy chief minister Ajit Pawar on Tuesday said the cabinet would soon approve the Pune-Nashik semi high speed corridor project to ensure that its work started as early as possible.

The ministry of railways approved the project last month. Pawar held a meeting to discuss the project with the authorities of the Maharashtra Rail Infrastructure Development Corporation Limited (MRIDC) on Tuesday. "A presentation on the project was made before Pawar as well the MLAs present," a source in the MRIDC said.
The cost of the project has been pegged at Rs16,039 crore. The length of the corridor would be around 235.15km.
The travel time from Pune to Nashik would be an hour and 45 minutes once the semi-high speed corridor is ready. The MRIDC will be developing some high speed trains, which will ply on the corridor with regular trains. The high speed trains will initially have six coaches and run at a speed of 200kmph.

The corridor will pass through Pune, Ahmednagar and Nashik, providing connectivity to industrial zones such as Alandi, Chakan, Khed, Manchar and Narayangaon, among others.

https://www.maharail.com/project-pune_nashik.php

Salient features:

  • Length: 235.15 Km
  • Speed Potential: Semi high speed with 200 KMPH
  • Travel time from Pune to Nashik: 2:00 hrs
  • Stations proposed: 24
  • Tunnels: 18
  • Project Cost: Approx. 13800 Crores (Excluding Taxes)
  • Completion period: 1200 Days from financial closure